introduction to instruction manual

1st Choice Chillers | Products | Trouble Shooting | Manual | Load Sizing | Sitemap | Links | Clients | Components | Get a Quote

1.0 | 2.0 | 3.0 | 4.0 | 5.0 | 6.0 | 7.0 | 8.0 | 9.0 | 10.0 | 11.0 | 12.0 | 13.0 | 14.0-

 

Chillers

Air Chillers

Water Chillers

Remote Chillers

Film Chillers

Mold Chillers

Packaged Chillers

-

Modular

Water/Glycol

Condenserless

Outdoor Air Cooled

-

Tank Sets

Chiller Tanks

Tower Water Tanks

Pre-Start-Up

7.0.0

Pre-Start-Up

7.1.0

DO NOT switch unit on. Make a complete visual check of unit for possible damage sustained during installation.

7.2.0

WITH POWER OFF Check all terminal screws in control panel, making sure they are tight.

7.3.0

Fill reservoir through fill pipe. Replace fill cap after filling (use our fill cap, it has a vent hole to protect the tank from expansion and contraction).

7.4.0

A minimum of eight (24) hours before start-up and with chiller switch in "off" position, turn on the supply disconnect. This allows the compressor crankcase heater to evaporate the refrigerant in the crankcase oil.

7.5.0

A process heat load must be available to the chiller for start-up.

   

1.0 | 2.0 | 3.0 | 4.0 | 5.0 | 6.0 | 7.0 | 8.0 | 9.0 | 10.0 | 11.0 | 12.0 | 13.0 | 14.0

   
-

Copyright © 2008 | 1st Choice Portable Chillers | All rights reserved

 
1st Choice Portable Chillers, 111 Esna Park Drive, Unit 7, Markham, Ontario, L3R 1H2
Toll Free: 1,877. 513. 8310 ~ Email: sales@1stchoicechillers.com