Pre-Start Up


7.0.0

Pre-Start Up

7.1.0

DO NOT switch unit on. Make a complete visual check of unit for possible damage sustained during installation.

   

7.2.0

WITH POWER OFF Check all terminal screws in control panel, making sure they are tight.

   

7.3.0

Fill reservoir through fill pipe. Replace fill cap after filling (use our fill cap, it has a vent hole to protect the tank from expansion and contraction).

   

7.4.0

A minimum of eight (24) hours before start-up and with chiller switch in "off" position, turn on the supply disconnect. This allows the compressor crankcase heater to evaporate the refrigerant in the crankcase oil.

   

7.5.0

A process heat load must be available to the chiller for start-up.

 