Pre-Start-Up
|
7.0.0
|
Pre-Start-Up
|
|
7.1.0
|
DO NOT switch unit on. Make a complete visual
check of unit for possible damage sustained during installation.
|
|
7.2.0
|
WITH POWER OFF Check all terminal screws in
control panel, making sure they are tight.
|
|
7.3.0
|
Fill reservoir through fill pipe. Replace fill cap after
filling (use our fill cap, it has a vent hole to protect the
tank from expansion and contraction).
|
|
7.4.0
|
A minimum of eight (24) hours before start-up and with chiller
switch in "off" position, turn on the supply disconnect. This
allows the compressor crankcase heater to evaporate the refrigerant
in the crankcase oil.
|
|
7.5.0
|
A process heat load must be available to the chiller for
start-up.
|
| |
|
|
|
| |
|
| - |
|
Copyright
© 2008 | 1st Choice Portable Chillers | All rights reserved
|
| |
1st
Choice Portable Chillers, 111 Esna
Park Drive, Unit 7, Markham, Ontario, L3R 1H2
Toll Free: 1,877. 513. 8310 ~ Email: sales@1stchoicechillers.com |