Pre-Start-Up
|
7.0.0 |
Pre-Start-Up |
|
7.1.0 |
DO NOT switch unit on. Make a complete visual
check of unit for possible damage sustained during installation. |
|
7.2.0 |
WITH POWER OFF Check all terminal screws in
control panel, making sure they are tight. |
|
7.3.0 |
Fill reservoir through fill pipe. Replace fill cap after
filling (use our fill cap, it has a vent hole to protect the
tank from expansion and contraction). |
|
7.4.0 |
A minimum of eight (24) hours before start-up and with chiller
switch in "off" position, turn on the supply disconnect. This
allows the compressor crankcase heater to evaporate the refrigerant
in the crankcase oil. |
|
7.5.0 |
A process heat load must be available to the chiller for
start-up. |
| |
|
1.0 | 2.0 | 3.0 | 4.0 | 5.0 | 6.0 | 7.0 | 8.0 | 9.0 | 10.0 | 11.0 | 12.0 | 13.0 | 14.0 |
|
| |
|
| - |
|
Copyright © 2010 | 1st Choice Portable Chillers | All rights reserved |
1st
Choice Portable Chillers, 111 Esna
Park Drive, Unit 7, Markham, Ontario, L3R 1H2
Toll Free: 1,877. 513. 8310 ~ Email: sales@1stchoicechillers.com |